Payment Calculator

Interim Payment Certificate Calculator

Calculate interim payment certificates for construction projects with retention, advance recovery, and materials on site

Contract Details

Enter contract value, work completed, materials, retention, and advance payment

Total contract value including all agreed variations

Cumulative percentage of work completed to date

Value of unfixed materials properly stored on site

Retention deducted from each certificate (default 10%)

Total advance payment received at start of project

Percentage of advance recovered per certificate (default 10%)

Total of all previous certificates paid

Frequently Asked Questions

What is an Interim Payment Certificate (IPC) in construction?

An Interim Payment Certificate (IPC) is a document used in construction contracts to certify the value of work completed during a specific period. It serves as the basis for progress payments to contractors, typically issued monthly, and includes work done, materials on site, and applicable deductions like retention and advance recovery.

How is retention calculated on construction payment certificates?

Retention is typically calculated as a percentage (usually 5-10%) of the gross valuation (work completed + materials on site). It's deducted from each payment certificate and held by the employer as security for contract performance. Half is often released upon practical completion, with the remainder upon final settlement.

What is advance payment recovery and how does it work?

Advance payment recovery is the process of recovering the upfront payment given to contractors at project start. Recovery typically starts after a certain percentage of work is completed (often 20-30%) and is deducted as a fixed percentage from each subsequent payment certificate until fully recovered.

Can materials on site be included in payment certificates?

Yes, materials on site that are properly stored, insured, and intended for the project can be included in payment certificates. Their value is typically included at cost without profit, and they must be properly documented with delivery notes and storage receipts.

What happens if a payment certificate is not paid on time in Saudi Arabia?

Late payment in Saudi Arabia may entitle the contractor to interest charges as per Saudi construction law and contract terms. Contracts often specify payment periods (e.g., 30 days from certificate submission). Persistent delays can lead to contract disputes, suspension of work, or termination for employer default.